Shore Road East new & refurbished beach huts

Last updated 16th July 2019

The Project

Construction planned to start September 2019

The addition of 6 standard and 2 premier beach huts on a first floor extension above the existing 12 ground floor beach huts, plus the refurbishment of the existing 12 beach huts.

PROGRESS UPDATES

  • July 2019 Stepnell Ltd appointed as contractor
  • November 2018 Tender for construction issued
  • June 2018 Planning permission granted (Application APP/18/00165/F) for a first floor extension of 6 standard and 2 premier beach huts and the refurbishment of 12 existing ground floor beach huts.

Approved beach hut design

The plans

 Download the plans (PDF, 4Mb)

Existing beach huts at Shore Road East

Project Details

Budget £340,000
Funding BCP Council
Project Lead Anthony Rogers, Recreation Manager
Main contractor Stepnell Ltd

Press Releases

Poole Beaches online

For regular beach news & updates