Shore Road East new & refurbished beach huts

Last updated 17th August 2020

The Project

Completed summer 2020

As a major gateway for people visiting Poole Beaches, the project at Shore Road and Shore Road East offers the opportunity to create a greater sense of arrival and welcome to the area.

At Shore Road East 12 beach huts (nos 73-84) have been refurbished and a first floor extension built above, with 6 standard huts and 2 premier beach huts. These premier huts both have an L shaped balcony.

Works progress gallery Latest pictures 17th June 2020

9th June 2020

28th May 2020

21st March 2020

2nd March 2020

13th January 2020

16th December

21st November

25th September-12th November 2019

Approved beach hut designs, Shore Road East (Nos. 73-84)

The look

The plans

Also happening here:

New Plaza at Shore Road

  • Enhanced public area and seating, refurbished toilets and showers, new beach office and more …
  • Further details and progress pictures at the Shore Road project page

Frequently Asked Questions

What will the works cost?

The plaza works at Shore Road and new beach huts at Shore Road East will cost approximately £900,000 and be funded by BCP Council and a grant from the Coastal Communities Fund

When will these works take place?

Site work began in September 2019 and we hope to complete works during spring 2020, subject to COVID-19 working restrictions. Regular updates will be posted on site and on our website.

What times will the building site operate?

Monday - Friday from 7.30am - 6pm. Weekend working will be subject to approval.

Can I still use the prom during the works?

Yes, access along the prom will continue, although it will be narrower in width to allow for the building works. There may be short periods of time when the prom will be temporarily closed for example during a delivery.

Will the toilets remain open during the refurbishment?

While the toilet block is refurbished we will provide temporary units.

How can I contact the Beach Rangers Office during the works?

Telephone: 01202 708181

Why are you building new beach huts?

There are a significant number of people on the waiting list for a beach hut in this area; these new huts will help to meet this demand and reduce waiting time.

BEFORE WORKS: twelve single storey beach huts at Shore Road East

PROGRESS UPDATES

  • September 2019 Works started on site 2nd September
  • July 2019 Stepnell Ltd appointed as contractor
  • November 2018 Tender for construction issued
  • June 2018 Planning permission granted (Application APP/18/00165/F) for a first floor extension of 6 standard and 2 premier beach huts and the refurbishment of 12 existing ground floor beach huts.