Hamworthy Park 16 new beach huts

Last updated 24th June 2018

The Project

16 new wood-effect family beach huts in shades of blue, on the promenade at Hamworthy Park, close to the Outdoor Activity Centre and landing stage. 

Completed 22nd June 2018

Ground works began at the end of April and were allowed to cure prior to beach hut installation w/c 18th June.

The approved Beach Hut design

Our Environmental Development team are also carrying out improvement works at Hamworthy Park – read about them here

Hamworthy Park beach

The location for proposed beach huts x 16

Project Details

Budget £120,000
Funding Borough of Poole
Project Lead Anthony Rogers, Recreation Manager
Beach Hut design, build & installation Ecologic Developments